It is my understanding that if I don't need a neutral at a sub panel then I don't need to take the neutral to it.
Here is the scenario. There is a service disconnect at the shore line. We want to install a 480-volt 3-phase panel at the end of a 400' long fixed pier leading to floating docks. Transformers will be used on the floating docks. We won't need a neutral for anything, so I'm of the understanding that the neutral can stop at the service disconnect and doesn't need to be carried to the sub panel.
Right/wrong?
Thanks,
Here is the scenario. There is a service disconnect at the shore line. We want to install a 480-volt 3-phase panel at the end of a 400' long fixed pier leading to floating docks. Transformers will be used on the floating docks. We won't need a neutral for anything, so I'm of the understanding that the neutral can stop at the service disconnect and doesn't need to be carried to the sub panel.
Right/wrong?
Thanks,