Bill Davis
Member
- Location
- McDonough, GA
Hi,
I have engineering notes indicating the service for a new building be built as follows:
1. Install disconnnect for new building beside the meter.
2. Install feeder conductors underground from meter to existing disconnect at building 70' away.
3. Remove existing service from existing disconnect.
My question is does the grouping of disconnects for this application have to be at the meter?
I have engineering notes indicating the service for a new building be built as follows:
1. Install disconnnect for new building beside the meter.
2. Install feeder conductors underground from meter to existing disconnect at building 70' away.
3. Remove existing service from existing disconnect.
My question is does the grouping of disconnects for this application have to be at the meter?