- Location
- Lockport, IL
- Occupation
- Retired Electrical Engineer
Consider a large site with many buildings. In a Central Utility Plant (CUP), there are several diesel generators intended to provide Emergency, Legally Required Standby, and Optional Standby loads throughout the site. Conductors are run in a loop from the CUP to building to building to building, and back to the CUP. At each building, the main loop is tapped, conductors are brought into the building, and (through some appropriate distribution equipment) are connected to E, LRS, and OS transfer switches.
Question: Does the fact that the loop itself provides power to Emergency loads and to ?other than emergency? loads, as also does the feeder into each individual building, run afoul of 700.9, and in particular the new 2008 language in sub-paragraph (5)?
FWIW, I have one existing site with this configuration, and am designing another site with a similar configuration.
Question: Does the fact that the loop itself provides power to Emergency loads and to ?other than emergency? loads, as also does the feeder into each individual building, run afoul of 700.9, and in particular the new 2008 language in sub-paragraph (5)?
FWIW, I have one existing site with this configuration, and am designing another site with a similar configuration.