fordelectapp
Member
I am installing a new temporary/permanent service that is mounted on a pedestal outside. There is 200 amp service coming from underground to the pedestal. I want to install a 200 amp meter socket with a 200 amp panel on the pedestal. From this panel I will sub-feed 100 amp to an exsisting garage and also per code I need at least one outlet on this pedestal to be considered a service. In the future there will be a house built near the pedestal which will be sub-fed also with a 100 amp service. Anyhow long story short the local inspector suggested using a "feed through" panel for this application. I am not very familiar with this and wondered if anyone could help me on clarifying the difference of this type panel. And also would you suggest using this type panel? Thanks