So I just finished the slab work for a new church
I have a total of 31 conduits ranging in size between 3/4" and 1 1/4" all stubbed out of the concrete along a wall with the intent of these conduits entering the bottom of a 12" x 12" trough approx. 6' long
above this trough is to be 3 different 120/208 V panels
being mostly a service electrician, i thought this was a pretty common way to get this deck work complete (pipe into wireway, go wherever needed and pipe up into correct panel)
after reading art 376 metal wireways, i'm well over 30ccc for this wireway
can I separate this 6' long trough into 3 sections to keep the ccc below 30 with end caps and nipple between them (that seems silly)
or is this not a wireway at all and just a 12x12x6 foot long junction box?
I have a total of 31 conduits ranging in size between 3/4" and 1 1/4" all stubbed out of the concrete along a wall with the intent of these conduits entering the bottom of a 12" x 12" trough approx. 6' long
above this trough is to be 3 different 120/208 V panels
being mostly a service electrician, i thought this was a pretty common way to get this deck work complete (pipe into wireway, go wherever needed and pipe up into correct panel)
after reading art 376 metal wireways, i'm well over 30ccc for this wireway
can I separate this 6' long trough into 3 sections to keep the ccc below 30 with end caps and nipple between them (that seems silly)
or is this not a wireway at all and just a 12x12x6 foot long junction box?