I am having a tough time finding the parts to complete a parallel 4/0 service. I ran parallel 4/0 service conductors from utility pole to Milbank 200 amp underground meter socket.(long run) Now I can't seem to get the right lugs to terminate the two 4/0 conductors. The supplier I deal with has tried twice to give me a double lug connector and they are not fitting. I asked about this last week but would appreciate a few more details, I am having a tough time. Is there a special double lug that fits in the meter socket? Do you know who makes it or what does it look like? A don't believe the utility will allow a splice before the meter. Thanks again for the help!