Hi, I am working on a battery sizing for a substation. I have a whole lot of outdoor SF6 breakers and gang operated disconnect switches. The control power for breakers and switches is 125VDC. I consider the breaker sequence operation for peak load calcuations and all the relays associated with breakers for continuous and peak operation (i.e. 1 minute operation per IEEE485)
My question is with regards to the switches, these switches are killers, I mean they take about 15amp to operate. Infact I do not need them to operate on fault, they will be operated for maintnenace as required. So, considering their use should I include them either in my continuous or peak load calculations? Either way my battery size will go up...
any advise or discussion is really appreciated
thanks
My question is with regards to the switches, these switches are killers, I mean they take about 15amp to operate. Infact I do not need them to operate on fault, they will be operated for maintnenace as required. So, considering their use should I include them either in my continuous or peak load calculations? Either way my battery size will go up...
any advise or discussion is really appreciated
thanks