I hope someone here can help me with a question.
Just recently I was called to do some service work on two different machines, each using some standard american 60 Hz motors fed with high frequency circuits.
One was a very old machine in a saw mill using a motor/generator set with a 120Hz output feeding four of the motors, thru a 3P 120Hz/60Hz double throw bypass switch.
The other was for a different customer but also a saw. It had a more modern static VFD feeding some of the motors.
My service work on each was on some of the 60 Hz circuits.
My question is does the NEC require any special calc's or treatments for the high frequency branches or feeders? And same question if the branch conductors are mized in a raceway with both frequencies? I checked the NEC and all I found was the 430.120 Adjustable drives info.
On these installations the conductors and sizes looked to be no different than we would use for standard 60Hz motors.
And besides the NEC are there any non required but good standard practices things to do differently, besides special color codes or labeling?
You guys are a great resource. Thanks in advance.
Just recently I was called to do some service work on two different machines, each using some standard american 60 Hz motors fed with high frequency circuits.
One was a very old machine in a saw mill using a motor/generator set with a 120Hz output feeding four of the motors, thru a 3P 120Hz/60Hz double throw bypass switch.
The other was for a different customer but also a saw. It had a more modern static VFD feeding some of the motors.
My service work on each was on some of the 60 Hz circuits.
My question is does the NEC require any special calc's or treatments for the high frequency branches or feeders? And same question if the branch conductors are mized in a raceway with both frequencies? I checked the NEC and all I found was the 430.120 Adjustable drives info.
On these installations the conductors and sizes looked to be no different than we would use for standard 60Hz motors.
And besides the NEC are there any non required but good standard practices things to do differently, besides special color codes or labeling?
You guys are a great resource. Thanks in advance.