In an industrial project I have 3 runs of 1000 A 480V/3 Bus Duct. I also have 3 runs of 600 A 208V/3 Bus Duct and 3 runs of 200A 240v/3 Bus duct. Do I have to include the entire load in the service calculations? There is no way there will be that much load connected.