Ok here is the scenario. PVC can be used but must be concrete encased. They call for (2) pipes to be run under slab on grade so accoriding to spec it must be RGS. Why wouldn't you just use PVC and put it IN the slab on grade thus fullfilling the concrete encasement requirment. Do you think just because the say to run it UNDER slab that's how it should be run?