Installing new, and relocating 2 x 4 and 2 x 2 troffers in an office environment. 410.36(B) tells me that the suspended ceiling framing members that I am laying the troffers in, must be fastened to each other and shall be securely attached to the building structure at appropriate intervals. Also, the fixtures should be securely fastened to the framing members by mechanical means. I am independently supporting each fixture because it seems safer that way but I am also reading in some of the threads here on this site that independently supporting the fixtures is also in the building code. I am ignorant when it comes to the IBC, so could someone with more experience with the IBC help me find just where in the IBC this requirement is located? My state is on the 2006 IBC, but the only copy I have is going to be the 2009. Thanks for the help.