I have a question. We have been asked to install a 400 amp 120/208v 3 ph solid neutral transfer switch right next to the existing MCC. My plan is to load out of main to normal line on xfr switch, then from load out of xfr switch to existing load conductors in mcc. If I run all three hots into the xfr switch do I need to run the neutral with them into switch and back?