how are the payment terms usually spelled out in a bid for a basic retail store tenant space?
I have did a few for existing customers and usually requested 20% at contract signing, (if there is a fixture packe to be ordered), 50% at an inspection point, (like wall or ceiling close) and the remaining 30% at final.
These jobs usually move really fast and are done sometimes in just a week
I have bid quite a few for out of town or state contractors and never have heard anything back
Is asking for a pecentage at signing limiting my chances of landing these projects?