Lady Engineer
Senior Member
- Location
- New Jersey
I designed this job, which required a new 5KV unit substation. Unit sub has (2) 2MVA transformers, with a 3000A switchboard (480V), tie breaker, etc. The unit sub hasn't been installed, but the steel supports are installed.
I get a call from the Electrical Forman, and he says, "Ma'am, we have a real problem out here. The piping guy is installing his 2' water pipe over my unit substation." I said, "What, he was supposed to turn the pipe avoiding running over the substation, and hang the pipe over the work space in front of the unit substation." (the pipe would be about 15' A.F.F.) "Well, too late, he has his piping installed.", he says. The foreman then says, "Well, he told me that he would run it 2" above the those 2 MVA transformers., but I said I guess we don't need conduits coming out of the unit substation." LOL Wow... :happyno:
This foreman is a smart cookie, and has been very good on the job. Can you imagine if he didn't catch that before they installed the unit substation.
I get a call from the Electrical Forman, and he says, "Ma'am, we have a real problem out here. The piping guy is installing his 2' water pipe over my unit substation." I said, "What, he was supposed to turn the pipe avoiding running over the substation, and hang the pipe over the work space in front of the unit substation." (the pipe would be about 15' A.F.F.) "Well, too late, he has his piping installed.", he says. The foreman then says, "Well, he told me that he would run it 2" above the those 2 MVA transformers., but I said I guess we don't need conduits coming out of the unit substation." LOL Wow... :happyno:
This foreman is a smart cookie, and has been very good on the job. Can you imagine if he didn't catch that before they installed the unit substation.