I am being asked to revise my bid for a two story 40 unit building. The issue is the utilities will not allow the meters installed inside the parking garage. All the other utilities in this area allow the meters installed inside with a variance request. It is a 1200A 208/120 3 phase service. The units will be fed single phase via the meter stack. (Each unit has its own meter) What would be the easiest way to install the SER feeders to the inside of the parking garage as the owner does not want anything installed on the exterior of the building. I was thinking of installing 6" PVC sleeves when they pour the foundation and then running 4" PVC conduit to a 8" x 8" x ?' trough on the inside. I was going to run three feeders thru the 4" PVC. From the trough we will be installing conduit sleeves up to the ceiling, where the general installs a soffit after the feeders are installed. Any suggestions or better ideas are greatly appreciated.
Than you in advance
Than you in advance