I fyour pricing a change order and the ckt is listed on the panel schedule but all they did was add it to the floor plan would you charge for it? I would say it was owed to them based on being on the schedule regardless if it was shown on the floor plan. Thanks.
 

petersonra

Senior Member
Location
Northern illinois
Occupation
engineer
I kind of agree, but it depends. I think you have some obligation for that work unless you specifically declaimed it based on the idea that if the panel schedule shows a breaker you should have known that there was field wiring associated with it.

Some of this also depends on your relationship with the customer, and just how much it is going to cost to do the work. If it is a good customer and it is a relatively cheap fix, you should have already done it.

If the customer is a cheap skate who is nickle and diming you to death, I would be less inclined to such a gesture.
 