Hendrix
Senior Member
- Location
- New England
I just looked at a job where the EC ran SEU to a sub panel. I told him that he needed to run SER. He asked if he could run a seperate equipment gnd to the sub panel, instead of changing over to SER. I said "I don't think so" but can't find the code section where it states that the conductors be run in the same raceway. Cand someone advise?