lavacano
Chadwick Ferguson, Safe and Sound Electric
- Location
- Washington State
- Occupation
- 02 master
Hi all,
I have a client with a 320a service feeding 2 main disconnect boxes then remotely 2 200a main breaker panels. In the heavily loaded panel I found circuits like 120v Electric Gate, Refer, Micro and an interlock for a generator.
I have installed a ATS on the generator and this heavily loaded panel. My client has been in the practice of turning off their 2 furnaces and manually switching over to Gen power.
I would like to make the whole system turnkey.
Instead of pulling all 6 240v branch feeders into the non switched panel, shouldn't I be able to pull 2 240v branch feeders (1 from each of the 2 furnaces) into the non switched panel, this should to my knowlege disable the furnace when power is on Gen only. Now I know there might be some talk about different equipment behaving differently but on 99% of the furnaces out there disconnecting one of the 240v feeders should disable the thing (and its heat pumps) correct?
I have a client with a 320a service feeding 2 main disconnect boxes then remotely 2 200a main breaker panels. In the heavily loaded panel I found circuits like 120v Electric Gate, Refer, Micro and an interlock for a generator.
I have installed a ATS on the generator and this heavily loaded panel. My client has been in the practice of turning off their 2 furnaces and manually switching over to Gen power.
I would like to make the whole system turnkey.
Instead of pulling all 6 240v branch feeders into the non switched panel, shouldn't I be able to pull 2 240v branch feeders (1 from each of the 2 furnaces) into the non switched panel, this should to my knowlege disable the furnace when power is on Gen only. Now I know there might be some talk about different equipment behaving differently but on 99% of the furnaces out there disconnecting one of the 240v feeders should disable the thing (and its heat pumps) correct?