msheets
PE Electrical
- Location
- Salt Lake City, UT, USA
- Occupation
- Electrical Engineer
I am working on the design of the electrical system of the surface infrastructure of an underground metal mine. I recently received an inquiry about the requirements of keeping grounding beds separate from each other: the Substation Ground Bed and the Safety Ground Bed. As I am new to this type of system, I did some research and found many papers discussing this requirement from the 1980's and 1990's, but nothing in the last decade. One of the papers referenced the 1996 NEC Article 250, section 154, which is no longer printed in the current code book. I have been unsuccessful in locating the code sections (CFR or NEC) detailing this requirement and am suspicious as to whether it is still in effect. Does anyone know where I can verify this?
Thanks in advance.
Thanks in advance.