is it possible to run 5 wire 3 phase from one building to another on the load side of service.
 

augie47

Moderator
Staff member
Location
Tennessee
Occupation
State Electrical Inspector (Retired)
I have not seen it on the market, but I have seen a 5th condcutor added.
 

GPT

Member
Location
CT
is it possible to run 5 wire 3 phase from one building to another on the load side of service.
would 310.20 apply where it says not more than 3 single insulated conductors supported on a messenger.
 

augie47

Moderator
Staff member
Location
Tennessee
Occupation
State Electrical Inspector (Retired)
:D You are opening a whole new can of worms.
In everyday applications, I see quad-plex with a conductor added, if needed and the manufacturer ampacites of quad used,
If we really get down to brass tacks, most quad (or triplex) used as feeders is actually a "covered" wire and not insulated, so the insulation listed in 310.20 are not applicable.
If it is critical, I'd say you might end up with engineering documentation needed.
 

augie47

Moderator
Staff member
Location
Tennessee
Occupation
State Electrical Inspector (Retired)
There are some good questioins there for discussion. I just don't know the answers.
The "accepted" installations seem to ignore many of the actual Code issues
 