A/A Fuel GTX
Senior Member
- Location
- WI & AZ
- Occupation
- Electrician
MC cable as a 200A feeder. Junction box with a splice about mid run. Does the EGC from the MC cable need to be landed via a lug to the junction box? What if there were 2ea 200A feeders spliced in this junction box. Do both EGC's need to be terminated to the box?