Default Hot Tub Confusion

Hey guys, I'm confused about code requirements for Hot Tubs and equipotential bonding grid. The more I read 680.26 the more confused I get. Am I right to think that a packaged hot tub if installed in direct contact with the ground , or on pavers, or on concrete requires a copper grid around the perimeter of the tub extending 3ft out and the tub pump motor bonded to it and any Metallic conduit within 5 ft bonded to it? One part I read of a copper bonding grid #8 12" netting another part I read as Quantity 1 #8 copper ring around tub. If the grid is correct, the code requires all cross joints to be connected. I called several supply houses today for some type of preformed grid and they didn't know what I was talking about and never heard of equipotential bonding????. I tried to call the local inspector and he was on vacation til Monday and no one else could give me an answer. Am I right to think that if the hot tub is on a wood platform and extends 3 ft around the tub that no bonding is required? This hot tub I'm talking about is the everyday run of the mill type that they sell at these hot tub stores with a fiberglass shell- 50a 240v evidently this is new for the 2008 code, never done this before. Any help would be appreciated!!!!! I tried to look back on several posts but didn't find anything- Gary
Reply With Quote
  #2  
Old 07-29-2010, 05:33 PM
nakulak nakulak is offline
Senior Member
 
Join Date: Aug 2007
Posts: 2,710
Default

yes .
Reply With Quote
  #3  
Old 07-29-2010, 07:06 PM
RESI RESI is offline
Junior Member
 
Join Date: Jul 2009
Location: Newport News, VA
Posts: 28
Default

Ote- I ran into the exact same issue. I found a company that manufactures a pool bonding grid that comes in a 100 foot by 3 foot roll. The grid is on 1 foot squares and it is welded at each crossing point. I had to place it on the ground, under the pavers and bond it to the bonding connector that comes with the hot tub, usually inside the control box. I will get the name and possibly the part number for you. It costs about $500.00 per roll.
Reply With Quote
  #4  
Old 07-29-2010, 07:09 PM
RESI RESI is offline
Junior Member
 
Join Date: Jul 2009
Location: Newport News, VA
Posts: 28
Default

Ote- Here is a link to a company that sells 50 and 100 foot rolls.

http://www.erico.com/public/library/fep/LT1242.pdf
Reply With Quote
  #5  
Old 07-29-2010, 07:58 PM
hotwire1955 hotwire1955 is offline
Member
 
Join Date: Jan 2009
Location: nj
Posts: 92
Default

Quote:
Originally Posted by ote View Post
Hey guys, I'm confused about code requirements for Hot Tubs and equipotential bonding grid. The more I read 680.26 the more confused I get. Am I right to think that a packaged hot tub if installed in direct contact with the ground , or on pavers, or on concrete requires a copper grid around the perimeter of the tub extending 3ft out and the tub pump motor bonded to it and any Metallic conduit within 5 ft bonded to it? One part I read of a copper bonding grid #8 12" netting another part I read as Quantity 1 #8 copper ring around tub. If the grid is correct, the code requires all cross joints to be connected. I called several supply houses today for some type of preformed grid and they didn't know what I was talking about and never heard of equipotential bonding????. I tried to call the local inspector and he was on vacation til Monday and no one else could give me an answer. Am I right to think that if the hot tub is on a wood platform and extends 3 ft around the tub that no bonding is required? This hot tub I'm talking about is the everyday run of the mill type that they sell at these hot tub stores with a fiberglass shell- 50a 240v evidently this is new for the 2008 code, never done this before. Any help would be appreciated!!!!! I tried to look back on several posts but didn't find anything- Gary
Install a #8 solid bare copper conductor around the tub 18 to 24 " from inside wall around tub 4 to 6 inched below sub grade connect it to the bonding lug for the tub,you need to install a perimeter bond for paved or unpaved surfaces including wood. You also need a disconnect within sight of the tub

Last edited by hotwire1955; 07-29-2010 at 07:59 PM. Reason: spelling
Reply With Quote
  #6  
Old 07-29-2010, 08:03 PM
Dennis Alwon's Avatar
Dennis Alwon Dennis Alwon is online now
Senior Member
 
Join Date: Dec 2006
Location: Chapel Hill, NC
Posts: 13,870
Default

I agree with hotwire. You do not need a grid but you do need to bond. With most cases you can use the altenate means. 680.26(B)(2)(b)
__________________
4 Out Of 3 People Have Trouble With Fractions

The National Sarcasm Society
Like We Really Need Your Support
Reply With Quote
  #7  
Old 07-29-2010, 10:24 PM
Jim W in Tampa's Avatar
Jim W in Tampa Jim W in Tampa is offline
Senior Member
 
Join Date: Mar 2006
Location: Tampa Florida
Posts: 7,096
Default

Sounds stupid if its wood but i would run # 8 bare around it 2 times and call it a day.
Reply With Quote
  #8  
Old 07-30-2010, 06:32 AM
volt101's Avatar
volt101 volt101 is offline
Senior Member
 
Join Date: Dec 2003
Location: New Hampshire
Posts: 251
Default

Quote:
Originally Posted by Jim W in Tampa View Post
Sounds stupid if its wood but i would run # 8 bare around it 2 times and call it a day.
Do you get paid twice for doing that?
__________________
Jim
New Hampshire
Reply With Quote
  #9  
Old 07-30-2010, 10:16 AM
Jim W in Tampa's Avatar
Jim W in Tampa Jim W in Tampa is offline
Senior Member
 
Join Date: Mar 2006
Location: Tampa Florida
Posts: 7,096
Default

Quote:
Originally Posted by volt101 View Post
Do you get paid twice for doing that?
Never had to do it. But how else do you bond wood ?
Reply With Quote
  #10  
Old 07-30-2010, 03:49 PM
volt101's Avatar
volt101 volt101 is offline
Senior Member
 
Join Date: Dec 2003
Location: New Hampshire
Posts: 251
Default

Quote:
Originally Posted by Jim W in Tampa View Post
Never had to do it. But how else do you bond wood ?
Why twice? Doesn't once comply?
__________________
Jim
New Hampshire
Reply With Quote
Reply

SpecialBanner1 All Forums

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On