Thread: Lighting Allowance

  1. #1

    Lighting Allowance

    What is a lighting allowance and how does it fit into a bid?

  2. #2
    Join Date
    Mar 2003
    Location
    3rd Rock from the Sun
    Posts
    949
    It is the amout of money that you are allowing to go to the purchase of lighting fixtures.

    Say your bid on a job is $8000. and you are given $500 towards lighting fixtures.
    Your bid would be $8500 including a $500 lighting allowance.
    -Todd-

    -Delawhere?

    Shock Me, Make Me Feel Better.

  3. #3
    Join Date
    May 2005
    Location
    Richmond, Virginia
    Posts
    21,838
    In other words, you have to be able to supply all of the fixtures for that $500.

    I'd rather have the customer supply and deliver them, and I just install them.

    With my guidance, of course.
    Code references based on 2005 NEC
    Larry B. Fine
    Master Electrician
    Electrical Contractor
    Richmond, VA

  4. #4
    Join Date
    Dec 2006
    Location
    Chapel Hill, NC
    Posts
    26,458
    When I have an allowance I put my markup on it but the homeowners only know about the allowance. Thus a $3000.00 allowance would have an extra $600.00 mark up but the HO will only get to spend the $3000.00. If they go over they must pay the difference.

  5. #5
    Join Date
    Oct 2009
    Posts
    226

    fixture allowance disasters

    THE DOWNSIDE....using a previous post as guide...... the fixtures cost me $2400. i use $3000 as the lighting allowance. this would be fine and works well in a perfect world. but you all know what happens next. the home buyer (with the builders approval) goes to a lighting store and spends an additional $15000 in upgrades for which he pays for directly. the fixture store sends the builder a $1000 referral fee. the builder then gives me $500 of that. now i have $1100 my way towards fixtures. sounds great until it takes 2 men 6 hours to assemble, install, and hang crystal on the two story foyer. the third man of the crew is spending almost as much time uncrating while dealing with the mis labeled fixtures on the phone. then you find of the few that you have already installed at least 2 or 3 are in the wrong location. at this point your crew will be back the next day. at the end of the next day you are still facing more trips when the backordered fixtures arrive. at this point for the additional $500 you you have 3 men for an additional 8 hours and are looking at another 6 to 8 hours for 2 men, all the while the builder thinks he is over paying you.

  6. #6
    Join Date
    Jan 2008
    Posts
    7,502
    Quote Originally Posted by rodneee View Post
    THE DOWNSIDE....using a previous post as guide...... the fixtures cost me $2400. i use $3000 as the lighting allowance. this would be fine and works well in a perfect world. but you all know what happens next. the home buyer (with the builders approval) goes to a lighting store and spends an additional $15000 in upgrades for which he pays for directly. the fixture store sends the builder a $1000 referral fee. the builder then gives me $500 of that. now i have $1100 my way towards fixtures. sounds great until it takes 2 men 6 hours to assemble, install, and hang crystal on the two story foyer. the third man of the crew is spending almost as much time uncrating while dealing with the mis labeled fixtures on the phone. then you find of the few that you have already installed at least 2 or 3 are in the wrong location. at this point your crew will be back the next day. at the end of the next day you are still facing more trips when the backordered fixtures arrive. at this point for the additional $500 you you have 3 men for an additional 8 hours and are looking at another 6 to 8 hours for 2 men, all the while the builder thinks he is over paying you.
    There, there. Just let it all out and you will feel much better. :grin:

    And all this time the busy-bee homeowner is also changing things with the plumber, painter, landscaper...
    BB+/BB=?

  7. #7
    Join Date
    Sep 2008
    Location
    Florida
    Posts
    12

    Angry

    And don't forget the warranty.

  8. #8
    Join Date
    Mar 2006
    Location
    SW Florida
    Posts
    2,388
    Owner or builder supplied, I hung T & M. I like the KISS method. When parts were missing or broken you just hand the box back.
    Unlimited Electric Contractor/Standard Electric Inspector/Traffic Signal Inspector/Highway Lighting and Level One Traffic Signal Installer.

    I know you believe that you understand what you think I said but I'm sure you realize that what you heard is not what I meant.