In going over the example D1(a) in the 2008 NEC book, I noticed that the Bathroom Branch Circuit (1, 2-wire, 20A circuit) is not included in the load calculation.
Is this an omission or error of the authors? Or is there a section that I missed classifying this as an intermittent load that need not be accounted for in load calculations?