hi Guys, My GC wants me to do a 11 stories high rise with 107 apt and 1 commercial space on 2nd floor, my question is electrical room is on second floor can i bring my pvc conduits from slab to electrical room on second floor with PVC, than from MDP i have to run 2-4"conduits to every other floor for meter banks can i use pvc through floors and put fire caulking around it? they will be inside every electrical room that are in every floor. it will be a straight shot from second floor all the way to 11th floor?
some people tell me they have seen pvc in risers but i have always use EMT but in this case they dont want to expend extra money if its not needed