My local church just moved buildings and had to contract tennant appronment to a local contractor. The ahj required emergency lighting to be at a minimum candle watt and it did not pass. The E.C. had to drop lighting lower from the cieling to achieve required emergency lighting. After C of O the E.C. sent the pastor a bill for the extra work. I understand the E.C. needs to get paid if the plans called for the original lighting. My question is who should be responsible for the extra cost to pass this inspection the general contractor and engineer or the church. Thanks for your help