spgustin@gmail.com
New member
- Location
- Weeki Wachee, FL., USA
When I intercept an existing system service lateral and install a new service entrance rated automatic transfer switch and a new generator can I maintain a bond between neutral ground at the existing service entrance switchboard or do I have to change to the service entrance automatic transfer switch and then would I have to install equipment ground condoctors in that portion of the existing service lateral between the new ATS and the existing switchboard since that would then become a feeder and not a service lateral or can I maintain a bond for a neutral ground at the existing service entrance switchboard with the service lateral from the service transformer to the existing switchboard via the ATS?