Thread: Estimating outlets in CMU

  1. #1
    Join Date
    Sep 2017
    Location
    KY
    Posts
    4

    Estimating outlets in CMU

    I am currently quoting a job where the customer has requested they be installed in the block wall. My experience with this while working in the field has been it's very time consuming and lots of varying factors. Does anyone have a labor hour number that has worked fairly well for them? I don't want to price myself out of the job, but then again I don't want to take a bath.

  2. #2
    Join Date
    Sep 2017
    Location
    KY
    Posts
    4
    I guess I should have said customer wants outlets recessed in the block wall. May not have had that totally clear

  3. #3
    Join Date
    Jun 2016
    Location
    Tampa, FL, USA
    Posts
    867
    Is it a new wall being constructed or an existing wall with the roof in place?

    How will the wall be finished? Painted block? Stucco? Furring and drywall? Other?

  4. #4
    Join Date
    Sep 2017
    Location
    KY
    Posts
    4
    Quote Originally Posted by Coppersmith View Post
    Is it a new wall being constructed or an existing wall with the roof in place?

    How will the wall be finished? Painted block? Stucco? Furring and drywall? Other?
    It is a brand new building, all walls new. Painted. no other finish. All exterior walls are also going to be slushed out every cell with rebar every 2'. Interior slushed every 4'

  5. #5
    Join Date
    Jan 2013
    Location
    MA
    Posts
    264
    Each job is different. How many outlets, switches and other devices are going in the wall. How many wall need boxes in them. if it is only 10 to 15 boxes then I would just pre-assemble the box and length of EMT with a coupling on it. Cut enough stubs for going up the wall with a connector on it. Then just let the mason know where the boxes are going and he may add the stubs in as he goes up with the wall. Labor is maybe 10% more on a small job. On bigger jobs you may have a guy just watching the masons build the walls and need to add the stubs as the wall goes up. This can be time consuming but in the down time the journeyman can be building the boxes and stubs while the walls go up. Another 20% would be a fair assumption for this end.

    One thing we do is used colored duct tape on boxes and the stub ups. Brown for lighting, red for fire alarm, orange for e-circuits, blue for data, pink for specialty and good old grey for receptacles. This works out great because its gives you a visual layout of the wall as it goes up and its easy to verify and take the guess work out what is installed.

  6. #6
    Join Date
    Jun 2016
    Location
    Tampa, FL, USA
    Posts
    867
    Is this a dwelling or commercial? If a dwelling you can run NM and avoid the mason chasing.

    I don't know what "slushed" means.

  7. #7
    Join Date
    Dec 2012
    Location
    Placerville, CA, USA
    Posts
    17,966
    Quote Originally Posted by Coppersmith View Post
    Is this a dwelling or commercial? If a dwelling you can run NM and avoid the mason chasing.

    I don't know what "slushed" means.
    It means poured full of mortar/concrete for additional strength.

    In interior walls only one vertical column of blocks gets filled every four feet. And no rebar?
    Outside walls are all filled, with rebar on two foot spacing.

  8. #8
    Join Date
    Jun 2016
    Location
    Tampa, FL, USA
    Posts
    867
    Ahhh. I'm familiar with the process. I never heard that term before. It must be a commercial building then. I've only worked on one building where all the exterior walls were filled with concrete. Good way to hurricane-proof a building. All the work there was surface mount EMT.

  9. #9
    Join Date
    Dec 2012
    Location
    Placerville, CA, USA
    Posts
    17,966
    Quote Originally Posted by Coppersmith View Post
    Ahhh. I'm familiar with the process. I never heard that term before. It must be a commercial building then. I've only worked on one building where all the exterior walls were filled with concrete. Good way to hurricane-proof a building. All the work there was surface mount EMT.
    OP's customer wants flush. If it is commercial, cost will vary enormously with wall type and position relative to rebar.
    Clearly no easy way to pull pipe or NM to a box in a filled wall after construction.

    In EU land they would probably saw cut a shallow channel and mortar the wires over.

  10. #10
    Join Date
    Jun 2016
    Location
    Tampa, FL, USA
    Posts
    867
    Quote Originally Posted by GoldDigger View Post
    OP's customer wants flush. If it is commercial, cost will vary enormously with wall type and position relative to rebar.
    Clearly no easy way to pull pipe or NM to a box in a filled wall after construction.

    In EU land they would probably saw cut a shallow channel and mortar the wires over.
    I don't think NM is an option at all. It's not allowed embedded in concrete and no reason to use it if conduit is being run, THHN would be better.

    Mason chasing 4x4 boxes & mudrings with PVC conduit is the way to go with this job. And yes, it will be labor intensive.