Two buildings (same owner, same property) fed from the same pad mount transformer with an adjacent meter. Transformer and meter located half way between the buildings.
For this example lets say 240V, 1Phase, one has a 100A service and one has a 200A service but the total load for both (added together) is less than 200A, so the meter is 200A.
Each building has a main disconnect/over current protection at the building.
Does there need to be any additional disconnect (with or without over current) at the meter?
For this example lets say 240V, 1Phase, one has a 100A service and one has a 200A service but the total load for both (added together) is less than 200A, so the meter is 200A.
Each building has a main disconnect/over current protection at the building.
Does there need to be any additional disconnect (with or without over current) at the meter?