Would like to get some info from anyone who does mainly residential new construction.
Recently one of the builders I work for questioned the amount of time I was taking to do my rough in work.
The homes I am talking about are both ranch and two story. The ranches are 2000/2500 sq ft and the two stories are 2500/3200 sq ft.
When I rough in ,all boxes are spliced, home runs are pulled back, and service and sub panels if installed are in place.
He's got a E/C telling him that he can rough in a 2500 ft house in 2 8 hrs days with a 2 man crew.
I don't see it happening no matter how organized you are.
Anybody here care to share their time roughing a house this size. Thanks.
Recently one of the builders I work for questioned the amount of time I was taking to do my rough in work.
The homes I am talking about are both ranch and two story. The ranches are 2000/2500 sq ft and the two stories are 2500/3200 sq ft.
When I rough in ,all boxes are spliced, home runs are pulled back, and service and sub panels if installed are in place.
He's got a E/C telling him that he can rough in a 2500 ft house in 2 8 hrs days with a 2 man crew.
I don't see it happening no matter how organized you are.
Anybody here care to share their time roughing a house this size. Thanks.