I've got a primary metered facility, for which we're providing new 13.8kV S&C gear. Utility is bringing the 13.8kV to our new gear but the gear is client owned. Down stream of the gear I've got three pad mounts all of which have a ground loop and multiple ground rods around them. What should I provide for grounding at the gear itself?