I have 3 pieces of Service equipment for a Multi Family Building.One section is Under Ground Pull section,2nd one is 1200A service equipment with 1200A service disconnect,and 3rd piece is 400A service disconnct.These 3 pieces are seperated in different location but fed from Pull Section.My question is where should be GEC,MBJ.
I found per 250-24-B(Grounded service conductor shall be bonded to service disconnect Enclosure for each service disconnect).But I am not sure if I have to bond the Service Grounded conductor to Pull Section which is part of Service Equipment.Where should be GEC(CW & Ufer connection).
Thanks