A building separated by fire wall creating two building 1and 2. Utility transformer is outside on the slab. One set of service lateralis feeding building 1 and another is feeding building 2. Can run the feedersencased in concrete from the secondary side of the transformer to building 2going under the slab of building 1? what code section will support that?
Thanks,
Thanks,