I am working on a building that has 60 tenants and we are doing an electrical upgrade. We plan to gut out the electrical room and replace it with a new switchboard and meter banks.
My question is:
As a rule of thumb based on your experiences, how long would the power shut down have to be in order to gut out and re-new the electrical room?
If it'll take a long time, how would you approach giving temporary power to all the 60 tenants if the old meter bank will be demolished? I want to install new meter bank in place where the old meter bank was installed. All of these tenants are not sub-metered, they all have their dedicated main meter.
My question is:
As a rule of thumb based on your experiences, how long would the power shut down have to be in order to gut out and re-new the electrical room?
If it'll take a long time, how would you approach giving temporary power to all the 60 tenants if the old meter bank will be demolished? I want to install new meter bank in place where the old meter bank was installed. All of these tenants are not sub-metered, they all have their dedicated main meter.