hhsting
Senior Member
- Location
- Glen bunie, md, us
- Occupation
- Junior plan reviewer
I have drawings where main service switchboard is being replaced in kind. While switchboard is replacing there are two outside temporary generator powering distribution panels downstream. See below snapshot.
The two temporary generators are outside and feeders are coming into building. Question are multiple outside feeders allowed to be fed to the
building from the two temp generators or not? I looked at NEC 2017 Article 225.30 and found only one outside feeder is allowed but in this situation not sure
The two temporary generators are outside and feeders are coming into building. Question are multiple outside feeders allowed to be fed to the
building from the two temp generators or not? I looked at NEC 2017 Article 225.30 and found only one outside feeder is allowed but in this situation not sure
