I usually set a “skid” with a 6 space MLO panel and a couple of 20amp circuits with two GFCI receptacles for job site power.
It feeds from a source with a 2 pole breaker and 4 wire SO cord.
Inspector said I need a service disconnect for the temp.
Can that be a breaker retaining clip on the 2 pole breaker feeding the skid at the source or does it need to be in the skid panel itself?
First time I’ve encountered this
It feeds from a source with a 2 pole breaker and 4 wire SO cord.
Inspector said I need a service disconnect for the temp.
Can that be a breaker retaining clip on the 2 pole breaker feeding the skid at the source or does it need to be in the skid panel itself?