When was equipotential bonding of swimming pools first required by the NEC?
R rmoon New member Jul 14, 2009 #1 When was equipotential bonding of swimming pools first required by the NEC?
barbeer Senior Member Location Pinellas County, FL Jul 15, 2009 #2 The 2005 NEC renamed 680.26 "equipotential bonding" and added the 3' perimeter..... in 2002 it was just bonding and as long as I can remember you have had to bond ladders, motors.......
The 2005 NEC renamed 680.26 "equipotential bonding" and added the 3' perimeter..... in 2002 it was just bonding and as long as I can remember you have had to bond ladders, motors.......