brantmacga
Señor Member
- Location
- Georgia
- Occupation
- Former Child
I got a contract today for a job I bid awhile back, and I had some issues with some of the language included I wanted to ask y'all about.
1) the contract states we understand that we will not be paid if the GC isn't paid.
2) the GC wants unconditional lien waivers before releasing a check.
3) the GC wants the right to audit our books for the project; not just for change orders, but for the entire project.
4) the GC wants all payments held in a trust; this project is not bonded.
5) the GC wants us to provide 1 hr for every 50 hours on site for part of a composite clean-up crew. We are required to clean our work area as usual, but they want us to provide labor to be directed by their PM to clean the entire site.
I take issue with #1 as my labor, material, and subcontractors have to be paid regardless.
#2, we never provide lien waivers before a check; I know we still have rights to file a non-payment affidavit, but regardless, we just don't do it. We offer a copy of a conditional lien waiver that will be mailed once a check has cleared. All based on experience.
#3, just no.
#4, again, no.
#5, whatever. I've never worked with a GC that doesn't hire a clean-up crew.
There are also a couple of items outlining responsibility for things that are expressly excluded in my proposal. I asked for an addendum to the contract, and was told none would be given. The contract has been forwarded to our attorney for review, but I'm curious how standard some of these things are with other GC's.
At this point we're at a standstill over the lien waivers. I was told we could personally exchange lien waivers for a check, but that I would have to drive to their office 2/hrs away. I countered with the option of them coming to my office, or sending payment with the PM to exchange. They said no to both, and I'm saying no to a half day round trip to collect.
Sent from my iPhone using Tapatalk
1) the contract states we understand that we will not be paid if the GC isn't paid.
2) the GC wants unconditional lien waivers before releasing a check.
3) the GC wants the right to audit our books for the project; not just for change orders, but for the entire project.
4) the GC wants all payments held in a trust; this project is not bonded.
5) the GC wants us to provide 1 hr for every 50 hours on site for part of a composite clean-up crew. We are required to clean our work area as usual, but they want us to provide labor to be directed by their PM to clean the entire site.
I take issue with #1 as my labor, material, and subcontractors have to be paid regardless.
#2, we never provide lien waivers before a check; I know we still have rights to file a non-payment affidavit, but regardless, we just don't do it. We offer a copy of a conditional lien waiver that will be mailed once a check has cleared. All based on experience.
#3, just no.
#4, again, no.
#5, whatever. I've never worked with a GC that doesn't hire a clean-up crew.
There are also a couple of items outlining responsibility for things that are expressly excluded in my proposal. I asked for an addendum to the contract, and was told none would be given. The contract has been forwarded to our attorney for review, but I'm curious how standard some of these things are with other GC's.
At this point we're at a standstill over the lien waivers. I was told we could personally exchange lien waivers for a check, but that I would have to drive to their office 2/hrs away. I countered with the option of them coming to my office, or sending payment with the PM to exchange. They said no to both, and I'm saying no to a half day round trip to collect.
Sent from my iPhone using Tapatalk