Splicing in Extg. Loads & New Feeder

Status
Not open for further replies.

mstrlucky74

Senior Member
Location
NJ
Trying to determine if I’ll need to temp out the loads fromMCC being demolished as the max time for shutdown/down time is 12 hours at aclip. Thinking if I get DP-24A into place along with new conduit and wire tosplice locations, then I can kill power at switch feeding MCC then tiein/splice my loads and the new feeder feeding DP-24A although I think the swingover/splicingwill take longer than 12 hours even with conduits in place. Any thought?T hanks.

Oh by the way the extg. feed from the 800A switch to the 1600A MCC be sized for 800A not 1600A, correct?
 

Attachments

  • Pages from RFP - 24th Floor Electrical Panel Replacement 8.23.2017 (002).pdf
    126 KB · Views: 0
Last edited:
Status
Not open for further replies.
Top