- Location
- Tennessee NEC:2017
- Occupation
- Semi-Retired Electrician
The only panel change-out I have done I did in this manner:
Identified and labeled all circuits.
Had the POCO pull the meter.
Used a generator for lights, receptacles, etc.
Removed old panel(fuse panel)
Installed new breaker panel
Installed conductors and breakers and label
Wait for inspection
Have POCO reinstall meter.
This was simple because there was no one living in the house and the panel size, 200A, was the same, no change in the SE conductors. My question is, how do you guys handle a change-out like this? And how do you change one when there are people living in the house? Also, how do you figure charges for the time it takes to identify each circuit when they are not marked or marked very well?
Thanks!
Identified and labeled all circuits.
Had the POCO pull the meter.
Used a generator for lights, receptacles, etc.
Removed old panel(fuse panel)
Installed new breaker panel
Installed conductors and breakers and label
Wait for inspection
Have POCO reinstall meter.
This was simple because there was no one living in the house and the panel size, 200A, was the same, no change in the SE conductors. My question is, how do you guys handle a change-out like this? And how do you change one when there are people living in the house? Also, how do you figure charges for the time it takes to identify each circuit when they are not marked or marked very well?
Thanks!