    #16
    Originally posted by charlie b View Post
    That part is correct.

    That part is not correct. You need to be aware that anytime you do a calculation that involves three phases, the factor of "the square root of 3," or about 1.73, is going to come into the equation at some location.

    For your example, VA = (A) times (V) times (1.73). So the total VA is 36 x 480 x 1.73, or about 29,900 VA. Each phase would be assigned one third of that value, or 9,967 VA.

    Got it - thanks Charlie