FOFE a.munoz
Member
- Location
- SF Bay Area
I have a project where we changed out the service panel and we had to run the service conductors, in rigid conduit, under the house for about 5 feet before they were terminated in the panel. The city inspector is requiring that we encase the conduit in at least 2" of concrete for the 5 feet of conduit that is under the house.
We've never been required to do this before, but the inspector won't pass us unless we do it. I'm totally at a loss as to how we'd go about getting 2" of concrete to encase the conduit.
Have any of you had experience in encasing conduit in concrete?
We've never been required to do this before, but the inspector won't pass us unless we do it. I'm totally at a loss as to how we'd go about getting 2" of concrete to encase the conduit.
Have any of you had experience in encasing conduit in concrete?