Assume there are no of cranes working non simultaneously, what is the code ref for the main breaker of the cranes panel.

I went through 610.41 & 610.42 with nothing.
 

templdl

Senior Member
Location
Wisconsin
Assume there are no of cranes working non simultaneously, what is the code ref for the main breaker of the cranes panel.

I went through 610.41 & 610.42 with nothing.

Is there anything in place that would prevent more than one to be operated at the same time?
 