sheldonrf
Member
- Location
- Washington, DC, USA
I am designing a green roof, I have the roof setup as the following: (from the bottom up)
Concrete roof deck
Insulation layer (about 1" of styrofoam like material)
Waterproofing build up layer (about 6" thick)
Air Layer (1/2" thick)
Root barrier membrane (4mm thick or about 1/8")
Reservoir sheet (1 5/8" thick) - actually looks like some egg crate
Followed by either - gravel rock / pavers / "growth media" (I assume to be dirt) and grass all of these are in the general category of 3" deep
Here is my conundrum.... I am installing power throughout the roof area and I need to run conduits. My overall depth is generally about 12 inches. I can not run my conduits in the insulation layer as it will cause condensation issues on the slab in the space below (which is already at a VERY high humidity), the client understandably does not want roof penetrations all over the place for the multitudes of receptacles that I need to place everywhere. Would this application even be considered direct burial? There is no AHJ to go to and ask, I have to derive this through the NEC and tell them. I plan to install all schedule 80 PVC (but that can change). Any advice is greatly appreciated......
Concrete roof deck
Insulation layer (about 1" of styrofoam like material)
Waterproofing build up layer (about 6" thick)
Air Layer (1/2" thick)
Root barrier membrane (4mm thick or about 1/8")
Reservoir sheet (1 5/8" thick) - actually looks like some egg crate
Followed by either - gravel rock / pavers / "growth media" (I assume to be dirt) and grass all of these are in the general category of 3" deep
Here is my conundrum.... I am installing power throughout the roof area and I need to run conduits. My overall depth is generally about 12 inches. I can not run my conduits in the insulation layer as it will cause condensation issues on the slab in the space below (which is already at a VERY high humidity), the client understandably does not want roof penetrations all over the place for the multitudes of receptacles that I need to place everywhere. Would this application even be considered direct burial? There is no AHJ to go to and ask, I have to derive this through the NEC and tell them. I plan to install all schedule 80 PVC (but that can change). Any advice is greatly appreciated......