kyleapec
Member
- Location
- siloam springs arkansas
The engineer has sized the conductors per 60 degree column unless noted otherwise all the way from the switchgear. I am of the opinion that we can run 90 degree to the JB next to the VAVs or whatever equipment it is and only the flexible whip into the equipment would need to be sized according to the rating of the equipment. They are fixated on 310.15(B)(16) and 110.14(C), but I don't think it needs to be all the way back am I correct or am I missing a code somewhere.