I-2 group

Status
Not open for further replies.

hhsting

Senior Member
Location
Glen bunie, md, us
Occupation
Junior plan reviewer
I have interior renovation Group I-2 community based residential facility with supervised care 24 basis/assisted living. They are transformer space from nurses starion to open physical thearpy gym, threapy room and offices.

Following questions:

1. Being I-2 IBC 2015 says must have backup generstor with essiential system. However, would they physical therapy gym require backup to essential system?

2. Does the 517 basic, general, critical, support level of patient care come into play for open physical therapy gym and therapy room?

3. Would wiring methods this sort of open threapy gym fall under 517 or 518?
 
Last edited: