bvano1983
Member
- Location
- El Paso, TX
250.52(A)(4) uses the word "encircling" does that mean the ring HAS to "encircle" the building or just has to have 20ft of an attempt to go around the building.
I agree otherwise it wouldn't be a loop. A cee only requires 20'IMHO, yes, the conductor must go all the way around the building or structure.
Pete