I'm doing a project at a minesite for a contractor trailer complex. I'm tapping the 13.8kV line and routing via direct burial 4-1/C #2 (one of which is a ground) around the property to terminate on 13.8kv-120/240v single phase transformers, swapping phases at each transformer to balance the load. My question has to do with the spacing between the the two trenches with the 600V rated cables. I read in another thread on the forum that the engineer used 12" spacing, but I couldn't find anywhere in the code where it addressed cable spacing for low voltage.
I have the spacing at 24" currently, but didn't know if I could reduce it.
Any suggestions?
I have the spacing at 24" currently, but didn't know if I could reduce it.
Any suggestions?