hhsting
Senior Member
- Location
- Glen bunie, md, us
- Occupation
- Junior plan reviewer
Attached sketch shows tap from utility CT to trough to PV disconnect in electrical room inside basement. However from PV disconnect goes straight to roof to switchboard named solar load. From switchboard feeder breaker goes to inverter on roof to strings and modules.
My question is does code require disconnect between PV disconnect and solar load switchboard outside building?
Sent from my SM-G935U using Tapatalk
My question is does code require disconnect between PV disconnect and solar load switchboard outside building?
Sent from my SM-G935U using Tapatalk