The study is one thing, accurate data collection is another issue. Depends upon how clean/clear existing system parts (i.e. identifiable) are as well as existing documentation and the accuracy thereof. Unless I had some idea of the facility, I'd NEVER suggest a per unit cost for a study if I also had to walk it down to begin with, but that's me.
I'm actually starting a large walk-down tomorrow that I have 4.5 months to complete; starts w/ 12.5 and works its way down. The customer (thus far) will be doing the study w/ my data. I hope to sell doing the study too though.